Monday, February 16, 2009

Week 27: finishing touches

People we are in the home stretch...

THIS WEEK... We need to...
Pick hardware for kitchen & baths
(maybe get it installed)
Find a ceiling fan/light fixture for master bedroom
(install)
Find a light fixture for dining room
(install)
Install plumbing fixtures (kitchen & bath)
Get broken tile fixed & sealed - scheduled for friday
Order closet doors for last room (install)
Follow up with Arcadia Sash & Door for door hardware
Buy a new mailbox (ours is missing)
Follow up with interior painter (paint on window, curtain hardware & toilet)
Have shower glass installed
Continue to empty house of construction trash
Buy curtains & hardware for bedrooms & baths
Organize Sears deliveries (Ovens (ASAP), refrigerator & dishwasher)
Figure out who can install appliances (hehehehe)
Schedule final Fire inspection
Complete Public Works Paper work (collecting paperwork, waiting on d.r. to get correct numbers)
Schedule FINAL inspection

It looks like a long list... but really... it's just time... and luck :)...

It is so NICE to have a long list... and NOT one million people to manage...

Next week.
The floors get finished and we start move in FRIDAY!!!

It's hard to believe we're at the end...

BOLD = DONE